Inspect

A risk-based, specification-driven method that produces the same traceable evidence on every engagement, from a single factory witness test to a full commissioning assignment.

[01]Execution methodology

  1. 01

    Scope & document review

    Confirm assets, specifications, drawings, acceptance criteria and responsibilities.

  2. 02

    Inspection & test planning

    Prepare a risk-based ITP, method statements, safety controls and required instruments.

  3. 03

    Field or factory execution

    Conduct agreed inspections, tests, sampling, witness points and evidence capture.

  4. 04

    Findings & NCRs

    Record deviations, classify risk and issue clear corrective-action requirements.

  5. 05

    Verification & close-out

    Review corrective actions, repeat agreed tests and update punch lists.

  6. 06

    Final report & handover

    Deliver traceable reports, an outstanding-item register and recommendations.

[02]Reference frameworks

Inspection and test plans are built around your approved specifications, contract requirements and the applicable current IS/IEC standards and electrical regulations.

IEC 62446-1

Grid-connected PV: documentation, commissioning tests & inspection

Used for · Handover documentation and commissioning test regime

IEC TS 62446-3

Outdoor infrared thermography of PV modules & plants

Used for · Drone and handheld thermal surveys

IEC TS 60904-13

Electroluminescence of photovoltaic modules

Used for · EL image capture and interpretation

IEC 61724-1

PV system performance monitoring

Used for · Performance-ratio and yield reviews

IEC 62933

Electrical energy storage systems (series)

Used for · BESS safety and integration reference

CSERC regulations

Intra-state open access in Chhattisgarh, as amended

Used for · Open-access feasibility and landed cost

Referencing a standard describes how work is planned. It is not a claim of certification, accreditation or statutory authority.
[03]Quality & compliance

  • Use approved specifications, contract requirements and applicable current IS/IEC standards and electrical regulations.
  • Check instrument calibration status and retain measurement traceability.
  • Use documented acceptance criteria and record deviations transparently.
  • Separate inspection findings from certification, statutory approval and laboratory test results.
  • Use qualified and authorized personnel where the law, OEM or project requires them.
  • Where an accredited test report or statutory sign-off is required, Ventorix coordinates with appropriately accredited or authorized organizations, subject to their scope and availability.
[04]Engagement models

01

Pre-dispatch / factory inspection

Equipment document review, agreed sampling and witness testing.

02

Pre-commissioning & commissioning

Site testing, punch list and handover documentation.

03

Independent quality assurance

Inspection plans, site quality surveillance and NCR management.

04

Specialist diagnostics

IV-curve, EL coordination, thermography and targeted fault investigation.

05

BESS & electrical systems review

Interface checks, FAT/SAT coordination and commissioning support.

06

Performance audit & O&M support

Recurring inspections, data review and improvement plans.

07

Engineering & procurement advisory

Technical specification, BOQ/BOM and OEM offer evaluation.

[05]Typical deliverables

Every finding is recorded, classified and closed out, with measurements traceable to instruments, dates and acceptance criteria.

ITPDOC-01

Scope of work & ITP

Defines assets, inspection points, criteria and responsibilities.

CHKDOC-02

Checklists & test sheets

Observed condition, measurements, instrument details and results.

NCRDOC-03

NCR & corrective action log

Deviation, severity, action owner, due date and closure.

IMGDOC-04

Photo & thermal evidence

Supports traceability and investigation of observed issues.

DOSDOC-05

Commissioning dossier

Approved test records, punch-list status and handover documents.

RPTDOC-06

Final technical report

Findings, limitations, risks and recommended actions.